Monument Realty is happy to announce that Ryan Homes has just begun construction of two model homes for the first phase of Bloom MV. The model homes will be located just off Montgomery Village Avenue, on the new Tall Oaks Road. The VIP sales launch will begin in August and the public grand opening is planned for September. The first new Bloom MV homeowners are expected to move into this new community by the end of this year. Sizes, prices and layouts are not currently available, but interested residents should e-mail This email address is being protected from spambots. You need JavaScript enabled to view it. to be added to an interest list.

Construction is ongoing in Areas 4 and 5, with the construction team working on water and sewer installation, final grading and street installation. Over the coming months, the community can expect to see the installation of Tall Oaks Road from Montgomery Village Avenue to Arrowhead Road, and the construction of the first new homes along that road. In Area 5, Green Village Drive will be installed off Stewartown Road and the first new homes along that road should be under construction by the fall.

Site development work on phase two will begin next, with Area 1 (118 townhomes), Area 3B (19 single-family detached homes) and the new park all expected to start construction this summer. Delivery of the new park is still anticipated by the end of 2021.

The stream restoration planning to enhance the open space area and improve the health of the stream valley is continuing. RES, a national ecosystem restoration and water resource expert, continues to work with the State Highway Administration (SHA) and the county on design and permitting for the stream restoration work, which is expected to be completed by the end of 2022. In the meantime, some afforestation will take place in the stream valley park in advance of the stream restoration. By the end of the project, over 2,800 new trees (and additional shrubs and plantings) will have been added.

Lastly, the final site plan amendment for Areas 2, 3A and 6A will be submitted in Fall 2021. Construction on these areas is expected to begin in the second half of 2022.

Monument Realty extends their gratitude to the community for the continued support, patience and interest in the project as it finally takes shape. For more information or questions, call 202-777-2000 or e-mail This email address is being protected from spambots. You need JavaScript enabled to view it..